The Scottish Energy Compact — June 2026

Four Conditions.
Five Demands.
No New Legislation.

Scotland’s planning leverage is real, immediate, and finite. The Compact sets the terms under which hyperscale data centres may operate in Scotland. It is built entirely within devolved planning powers. It does not require new primary legislation. It requires only the political will to pick up a pen before the concrete is dry.

Condition 01

Firm Power

Contracted pathway to 100% dispatchable supply — developer bears full grid costs, not households

Condition 02

Community Levy

£15/MWh Community Energy Fund — energy efficiency and bill relief for local residents

Condition 03

Water Standards

Evaporative cooling prohibited — mandatory WUE declaration, SEPA Environmental Authorisation before consent

Condition 04

Infrastructure Setback

100m planning setback from 400kV infrastructure; cumulative field contour assessment required

The Argument

Why Scotland Needs a Compact, Not a Policy Statement

A 600MW data centre will generate 180–480 permanent jobs — mostly requiring skills local residents do not have — in exchange for the electricity of a small city, millions of litres of water per day, hidden bill increases for every household in the distribution area, and profits booked in Dublin, Seattle or Singapore.

By any measure, that is a poor bargain. Scotland is being offered the costs, the land, the water and the infrastructure burden. The value flows elsewhere.

The Compact does not argue that Scotland should reject data centre investment. It argues that Scotland should set the terms of that investment — as Ireland, the Netherlands and Singapore have all done with formal policies, moratoriums, or revised planning frameworks when their pipelines reached comparable scale.

The four conditions below are each grounded in a specific, identifiable harm or omission in the current consent process. They are proportionate to the scale of development being approved. They are enforceable through existing Section 75 planning obligation powers. They require no new Act of Parliament.

The Bargain As It Stands

Metric Current Framework Under the Compact
Household billsRise £145–225/yrReduced via levy credit
Grid costsSocialised to consumersDeveloper-funded
Water impactUnassessedCapped & published
EMF riskUnassessedPlanning setback + cumulative assessment
Electricity subsidy£84m/yr per 500MW to developers£52.5m/yr returned to communities (Condition 2)
Permanent jobsClaimed 3,400; actual ~180–480Contractual targets
Scottish benefitIndirect, speculativeDirect, contractual, permanent

The Constitutional Landscape

What Holyrood Can Do. What It Cannot. And Why the Compact Stays in Lane.

Any serious policy proposal for Scotland must be honest about the constitutional landscape. Electricity market regulation, grid charging methodology, and UK-wide subsidy design are reserved to Westminster under the Scotland Act. A Scottish Parliament that legislated to override GB-wide electricity market rules would be acting beyond its competence and would face immediate legal challenge.

This is not an argument for passivity. It is an argument for precision. Holyrood has substantial, largely unused leverage in the one area that matters most at this stage: planning consent. No data centre gets built without planning permission. Planning is devolved. The conditions attached to planning consent are the Scottish Government’s to set.

The Compact is built entirely within the green rows of the table opposite. It does not require reserved-powers legislation. It does not depend on Westminster cooperation. It depends only on the Scottish Government choosing to use powers it already holds.

Power Status Available Now?
Planning consent conditionsDevolvedYes
Community benefit obligations (s75)DevolvedYes
Environmental Impact Assessment requirementsDevolvedYes
Water abstraction licensing (SEPA)DevolvedYes
National Planning Framework (NPF4) guidanceDevolvedYes — update required
TNUoS / DUoS charging methodologyReserved (Ofgem)No — Westminster only
DSIT electricity subsidy proposalReservedNo — but can formally oppose
GB Capacity MarketReserved (DESNZ)No — Westminster only
North Sea gas licensingReserved (NSTA)No — Westminster only

Source: Scotland Act 1998 (as amended); Scottish Government devolved competencies. The Compact operates exclusively within the devolved rows.

Part One — The Four Conditions of Consent

What Every Facility Above 200MW Must Demonstrate

Each condition applies to any hyperscale data centre above 200MW IT load seeking planning consent in Scotland. Each is enforceable as a Section 75 planning obligation — a legally binding agreement between the developer and the planning authority, standard practice in major development consent. No new primary legislation is required. The conditions can begin operating immediately through a ministerial direction under the Town and Country Planning (Scotland) Act 1997, reinforced by a Planning Circular, and consolidated permanently through a targeted update to NPF4 Policy 24 (Digital Infrastructure). The mechanism is a ministerial decision. The timeline is a matter of political will, not legislative process.

Condition 01 — Firm Power & Renewable Generation

Every facility above 200MW must demonstrate, before planning consent is granted, a contracted pathway to firm, dispatchable power supply for 100% of its maximum demand. The developer must accept full cost-reflective charges for all grid infrastructure required to serve the development. No grid reinforcement, capacity market, or balancing costs triggered by the facility may be socialised onto the wider consumer base.

The firm supply pathway may be met through long-term power purchase agreements from dedicated dispatchable renewable sources, on-site generation, or other technologies capable of sustained delivery without drawing on grid balancing services at consumer cost. Gas peaking capacity, where included, requires a binding phase-out schedule as a condition of consent.

The developer must additionally contract renewable generation capacity plus grid-scale battery storage equivalent to at least 150% of average annual energy demand. This is not a requirement to match supply at every moment — it is a requirement to demonstrate a credible, contracted path to net-zero energy consumption before consent is granted, not after.

What this condition is designed to prevent. The UK Government’s DSIT programme offers hyperscale data centres a discount of up to £24 per MWh on electricity costs. For a 500MW facility consuming approximately 3,500 GWh per year, that is £84 million per year in public subsidy — flowing to corporations whose combined market capitalisation exceeds $5 trillion. Across the Scottish pipeline as a whole, the annual subsidy transfer could exceed £1 billion. Paid by every household in Great Britain through their energy bills, whether they know it or not.

The UK Government’s own £24/MWh discount is an admission that clean, firm electricity at this scale costs more than the market currently prices it. Condition 1 does not withdraw that subsidy — only Westminster can do that, and the Scottish Government should press for it (see Westminster Ask W1). What Condition 1 does is require the developer to demonstrate, before consent, that the facility has a viable power supply that does not depend on the grid costs and balancing services currently being paid by Scottish households. The gap between what developers pay today and what Condition 1 requires is the precise amount being externalised onto consumers. Requiring developers to internalise it is not a barrier to investment. It is an honest price.
Condition 02 — Community Energy Levy (Section 75)

A mandatory Section 75 obligation requires each developer to contribute £15 per MWh of electricity consumed into a ring-fenced Community Energy Fund, administered by the relevant local authority.

The Fund is dedicated exclusively to reducing energy costs for residential properties within the local authority area hosting the facility. It is applied to energy efficiency measures, insulation programmes, heat pump installations, and direct bill relief schemes — not to a council general fund, not to discretionary grants. The distribution methodology, eligibility criteria, and annual expenditure must be published. Every year the facility operates, the Fund operates.

For a 500MW facility consuming approximately 3,500 GWh per year, the levy generates £52.5 million per year for local household energy costs. For context: the UK Government’s £24/MWh DSIT discount to the same facility is worth £84 million per year — paid by every household in Great Britain through their energy bills, flowing to corporations whose combined market capitalisation exceeds $5 trillion. Westminster pays the developer £84 million. Condition 2 requires the developer to return £52.5 million to the communities hosting them. That is not redistribution. It is the minimum a just planning framework should require.

Mechanism: Section 75 of the Town and Country Planning (Scotland) Act 1997. A planning obligation specifying the per-MWh contribution rate, the administering authority, eligible expenditure categories, annual reporting requirements, and the enforcement mechanism in the event of non-payment. Community benefit obligations of this type are well-established in Scottish planning practice — analogous to wind farm community benefit funds, which typically deliver around £5,000 per MW per year. Condition 2 applies the same principle at a scale proportionate to the facility’s consumption and its impact on household bills. No new primary legislation is required.

Why the distribution mechanism matters. The Fund is administered by the local authority and applied through existing energy efficiency and housing programmes — not through electricity billing systems, which are regulated by Ofgem under reserved UK legislation and cannot be directed by a Scottish planning authority. The practical effect for residents is the same: lower energy costs, measurably and permanently, for as long as the facility operates. The legal mechanism is entirely within devolved powers.
Condition 03 — Water Impact & Cooling Standards

Closed-loop or air-side economisation cooling is mandatory for all hyperscale facilities above 200MW. Evaporative (wet tower) cooling is prohibited. A SEPA Environmental Authorisation for water abstraction must be confirmed in principle before planning consent is granted — not after.

This is not a default that can be argued away. A 500MW facility using evaporative cooling draws approximately 17–19 million litres per day from the water supply system — requiring a dedicated 450–600mm mains connection at sustained industrial pressure. Scotland’s existing water infrastructure was not designed to accommodate this demand. The proposed Auchtertool facility in Fife demonstrates the gap: Scottish Water confirmed that even at the developer’s own declared demand, the existing mains pipe is too small. Lomond Hills reservoirs — the primary drinking water source for Fife — stood at 21% of combined capacity in 2025, the lowest level in 30 years. The River Eden catchment, which feeds the same supply zone, has had abstraction licences suspended under SEPA’s Significant Scarcity designation in both 2022 and 2025. In May 2025 SEPA confirmed all of Scotland was at some level of water scarcity. Adding an evaporative cooling load of 17–19 million litres per day to a catchment already at its environmental limit is not a planning risk to be assessed and mitigated. It is a planning harm that cannot be consented.

Every applicant must submit a Water Usage Effectiveness (WUE) declaration using Green Grid standard methodology, independently verified, specifying the cooling system, the WUE target in litres per kWh of IT load, and the resulting maximum daily and annual abstraction volume. The water source must be named, the connection point agreed with Scottish Water, and the pipe diameter required must be specified. The applicant bears the full cost of any infrastructure upgrade to Scottish Water’s distribution network as a condition of consent. A cumulative abstraction assessment covering all proposed facilities drawing from the same catchment or Scottish Water supply zone must be submitted alongside the individual application. Annual WUE performance must be reported to SEPA and the planning authority, with all reports published. Facilities failing their declared WUE target within three years face a mandatory consent review.

Why this condition is non-discretionary. The prohibition on evaporative cooling is not a policy preference — it is a response to documented catchment conditions. SEPA’s own Significant Scarcity designations for Fife catchments (Eden, Leven, East Neuk) and the 30-year low in Lomond Hills reservoir storage mean that a Complex Environmental Authorisation for 17–19 million litres per day of abstraction from the same supply zone would, on current evidence, face refusal or conditions that make evaporative cooling operationally impossible. The Compact makes that position explicit at the planning stage rather than allowing consent to be granted without specifying the cooling system. A figure of 93,000 litres per day — such as that declared for Auchtertool — is consistent only with fully closed-loop cooling. Closed-loop cooling must therefore be a binding condition of consent, not an unstated assumption buried in a planning statement.

Mechanism: A ministerial direction to SEPA and all Scottish planning authorities, requiring mandatory WUE declarations and SEPA pre-authorisation as a condition of any application above 50MW being registered as valid. No primary legislation is required. The Cabinet Secretary for Net Zero and Energy can sign this direction.

Published sources, all publicly available. Water demand calculations: The Green Grid WUE White Paper #35 (thegreengrid.org); Lawrence Berkeley National Laboratory data centre water study (escholarship.org). Lomond Hills reservoir levels: Scottish Water Annual Report 2024/25 (scottishwater.co.uk). Fife catchment stress: SEPA Water Scarcity Report 15 May 2025; SEPA abstraction licence suspensions, Eden catchment (beta.sepa.scot). Auchtertool water claim and pipe capacity: The Courier, “Water chiefs speak out on Fife AI data centre supply claims” (thecourier.co.uk). Licensing framework: Environmental Authorisation (Scotland) Regulations 2018 (legislation.gov.uk). Infrastructure gap: ILI Group planning submission, Auchtertool (93,000 L/day declared); Green Grid WUE industry benchmark (1.8 L/kWh implies 17.3 million L/day for same facility).
Condition 04 — Infrastructure & Buffer Zones

A 500MW data centre requires grid connection infrastructure on the scale of a small power station: 275kV or 400kV overhead transmission lines carried on 56-metre steel lattice towers, and an on-site substation of 2 to 6 hectares. That infrastructure has a measurable electromagnetic field footprint extending beyond 100 metres. An independent cumulative impact assessment covering that infrastructure must be completed before consent is determined.

Standard 400kV towers stand approximately 56 metres and are spaced at approximately 370-metre intervals. The on-site substation — whether gas-insulated or air-insulated switchgear — occupies between 2 and 6 hectares of land. Published measured data for 400kV overhead lines shows magnetic field levels of 5–10 microtesla (µT) directly beneath the conductor, falling to approximately 0.2 µT at 120 metres and approaching background levels at 150 metres. The IARC classification of ELF magnetic fields as Group 2B (possibly carcinogenic to humans) is based on an observed association with childhood leukaemia in long-term residential exposure above 0.3–0.4 µT. On published field decay data, levels from a 400kV line exceed this epidemiological threshold out to approximately 60–80 metres from the conductor at typical operating loads.

The Compact requires a 100-metre planning setback from any new 275kV or 400kV overhead transmission conductor or substation perimeter fence to the nearest residential property, school, or hospital. This is not a health regulation — it is a planning protection grounded in measured field data. At 100 metres, published measurements show that fields from 400kV infrastructure approach background levels. The 2009 UK Government decision not to impose mandatory buffer zones on the existing network was a cost-benefit judgement about retrofitting requirements on infrastructure already in place. It does not bind Scotland’s planning framework for new infrastructure consented under its own planning system. Full public consultation on grid connection routes and substation siting must be completed before consent is determined. The applicant must publish a grid connection statement identifying all above-ground infrastructure, substation footprints, and modelled field contours at 50, 100, and 200 metres from the nearest residential properties.

Evidentiary basis for 100 metres. Measured magnetic field data for 400kV transmission lines shows levels exceeding the IARC Group 2B epidemiological threshold of 0.3–0.4 µT out to approximately 60–80 metres from the conductor, with fields approaching background at 100–120 metres. The 100-metre setback is the distance at which the infrastructure’s measurable field footprint ends on data published by the industry’s own sources and the German Federal Office for Radiation Protection.

Why the 2009 SAGE decision does not resolve this. The Written Ministerial Statement of October 2009 declined mandatory buffer zones because the cost-benefit case was not made for the existing network — a GB-wide cost-benefit judgement about infrastructure already in place that does not bind Scotland’s planning framework for new consents. The SAGE Second Interim Assessment (2010) separately concluded that reasonably practicable steps should be taken to site new substations away from residential properties. That principle has never been applied as a condition of planning consent in the data centre process. The Compact applies it.

Published sources, all publicly available. Field decay measurements: emfs.info, “Electric and magnetic fields from transmission overhead lines — 400kV specific data” (emfs.info/sources/overhead/specific/400-kv/); Bundesamt für Strahlenschutz (BfS), “Field strain due to high-voltage lines” (bfs.de). IARC Group 2B classification: IARC Monograph 80, Non-ionizing Radiation Part 1: Static and Extremely Low-Frequency (ELF) Electric and Magnetic Fields, 2002 (publications.iarc.fr). SAGE assessments: First Interim Assessment 2007 and Second Interim Assessment 2010, Energy Networks Association (energynetworks.org/publications). Government response: Written Ministerial Statement, October 2009; National Policy Statement EN-5 (gov.uk).

Part Two — Five Immediate Demands

What Can Be Done This Parliamentary Session

The full Compact requires an updated NPF4 and political commitment. The five demands below can each be acted upon within this parliamentary session using existing powers. None requires a new Act. Some require nothing more than a ministerial statement or letter to a planning authority.

1

Moratorium on consents above 200MW pending a cumulative impact assessment

Pause all data centre consents above 200MW IT load for twelve months. Commission a government-led cumulative impact assessment covering energy grid capacity, water catchment impact, consumer bill cost, and EMF infrastructure exposure. Twelve months. One assessment. Before the irreversible decisions are made. Ireland, the Netherlands and Singapore have all enacted similar pauses when their pipelines reached comparable scale. This is prudent governance, not obstruction.

Can be enacted now — no legislation required
2

Formally and publicly oppose the DSIT electricity subsidy

The Scottish Government should formally and publicly oppose the UK Government’s proposal to give data centre developers a £24/MWh electricity discount, and should refuse to facilitate the scheme in Scotland. A ministerial statement to the Scottish Parliament, followed by formal correspondence to DSIT, is the minimum required. The Scottish Government has expressed opposition to UK energy policy before. This is the appropriate occasion to do so again.

Can be enacted now — ministerial statement
3

Review and update NPF4 to require Compact compliance

National Planning Framework 4’s designation of “green” data centres as national developments streamlined consent at a time when the pipeline was a fraction of its current size. That designation must now be conditioned on Compact compliance. Planning authorities should be directed that national development status does not override the four Compact conditions — it co-exists with them. The mechanism is a ministerial direction to planning authorities, a Planning Circular clarifying how Policy 24 (Digital Infrastructure) applies to large-scale facilities, and a targeted Policy 24 update in the next NPF4 review — none of which requires primary legislation.

Requires ministerial direction and Planning Circular — no primary legislation
4

Issue a ministerial direction requiring standardised water assessments

The Cabinet Secretary for Net Zero and Energy should direct SEPA and all Scottish planning authorities to require a standardised water abstraction and cooling methodology assessment for any data centre application above 50MW, with all results published before consent is determined. A single ministerial direction covers the entire pipeline. It can be issued today. No legislation is required. No committee process. A direction, signed and published.

Can be enacted now — ministerial direction only
5

Publish the household cost impact within six months

Commission and publish, within six months, an independent assessment of the cumulative network cost impact of the current planning pipeline on Scottish household electricity bills. The methodology should be agreed with Ofgem, National Grid ESO, and consumer representatives. The results should be published in a form accessible to the public — not buried in a technical annex. The public deserves to know what is being built in their name and at their expense before more consents are granted.

Can be enacted now — commission report

Part Three — The Westminster Asks

What Scotland Should Demand from the UK Government

Several of the most significant levers sit with Westminster, not Holyrood. The Scottish Government cannot unilaterally reform grid charging methodology or cancel the DSIT subsidy. But it can use every available channel — Sewel conventions, intergovernmental frameworks, and direct public advocacy — to press for three specific changes.

These are not procedural requests. They are the conditions under which the current pipeline becomes genuinely fair to Scottish consumers rather than a transfer of public value to private capital.

The Scottish Government has spoken loudly on reserved matters before — on welfare, on immigration, on nuclear weapons. The question of who pays the electricity bill for hyperscale AI infrastructure is no less appropriate for formal, public advocacy.

Part Four — Act Now

Write to Your MSP

Every MSP in the Scottish Parliament has a constituency and regional role that includes potential data centre sites or households that will bear the grid cost. This is not a question of which party you support — it is a question of whether the government uses the powers it already holds before the window closes.

The Compact’s five immediate demands can all be acted upon before the end of this parliamentary session. The moratorium buys time. The ministerial direction on water costs nothing to implement. The opposition to the DSIT subsidy is a statement, not a statute. The household cost assessment is a commission. These are not legislative mountains. They are decisions.

This analysis may be freely reproduced for non-commercial campaign use with attribution to Michael Knox, June 2026.

Find Your MSP

Use the Scottish Parliament’s MSP finder to contact your constituency MSP and all seven regional MSPs for your area. Every Scottish voter has eight MSPs — constituency plus regional list.

Find your MSP → All current MSPs →

Template Letter

⚠ Before you send: Please personalise this letter. Add your town, a local detail, or your profession. Emails that read as personal carry far more weight with MSPs than identical form letters. Unedited copies are easy to dismiss — a sentence or two in your own words makes all the difference.

SUBJECT: Scottish Data Centre Planning — Four Conditions Holyrood Can Apply Now

Dear [MSP Name],

I am writing as a constituent from [your town/area] with urgent concerns about the environmental impact of hyperscale data centre development in Scotland. Twenty facilities are currently progressing through the planning system, yet not a single cumulative environmental impact assessment has been carried out. Consents are being granted individually, in isolation, with no assessment of their combined effect on Scotland’s water supply, electricity grid, or the health of local communities.

The water risk is immediate. A 500MW facility using evaporative cooling draws up to 19 million litres per day from the water supply system — equivalent to the daily consumption of a city the size of Perth. In Fife, where several sites are proposed, Lomond Hills reservoirs stood at 21% capacity in 2025, the lowest level in 30 years, and the River Eden catchment has had abstraction licences suspended twice due to water scarcity. No developer has been required to declare their cooling system or their true water demand before consent is granted.

The electricity supply position is equally unassessed. The combined demand of the current pipeline exceeds Scotland’s entire winter peak consumption, yet no assessment of grid capacity, infrastructure cost, or household bill impact has been published. Each facility requires grid connection infrastructure on the scale of a small power station — 56-metre steel lattice towers carrying 275kV or 400kV overhead lines, and substations of up to 6 hectares. Published field measurements show that electromagnetic fields from 400kV infrastructure exceed the threshold associated with childhood leukaemia risk in the IARC classification out to 60–80 metres from the conductor at typical operating loads. No cumulative EMF assessment has been required as a condition of any Scottish data centre consent.

The Scottish Energy Compact proposes four planning conditions that address each of these failures directly. Crucially, all four operate within devolved planning powers — they require no Westminster legislation, no reserved-powers override, and no new Act of the Scottish Parliament. They are planning conditions, attachable to consent by ministerial direction under existing powers today:

Condition 1 — Firm Power: The developer must demonstrate a contracted pathway to 100% dispatchable power supply at full cost-reflective grid charges before consent is granted. No grid reinforcement costs may be passed to consumers.

Condition 2 — Community Energy Fund: A mandatory Section 75 planning obligation requiring £15 per MWh consumed to be paid into a ring-fenced local energy fund for bill relief and insulation — entirely within devolved powers, consistent with established wind farm community benefit practice.

Condition 3 — Water and Cooling: Evaporative cooling is prohibited for facilities above 200MW. The developer must declare their cooling system and obtain SEPA Environmental Authorisation for water abstraction before — not after — planning consent is granted.

Condition 4 — EMF Buffer Zone: A mandatory 100-metre planning setback from any new high-voltage transmission conductor or substation to the nearest home, school, or hospital, grounded in published field decay data showing EMF levels approach background at that distance.

I would ask you to raise these conditions in the Scottish Parliament and to press the Cabinet Secretary for Net Zero and Energy to issue a ministerial direction applying them to all applications above 50MW. No primary legislation is required. The full analysis is at scottishenergycompact.co.uk.

Yours sincerely,

[Your full name]

[Your postcode]

Share This Campaign

The more people who read the evidence, the harder it becomes to ignore. Share this analysis with your neighbours, your local press, your community council, and anyone standing for election in Scotland.

ScottishEnergyCompact.scot

Scotland’s leverage is real, immediate, and finite

The Concrete Is Not Yet Dry.
The Argument Is Not Yet Lost.

The four Compact conditions require no new primary legislation. They require a minister to pick up a pen. The five demands can be enacted this session. The question is whether the government that claims to act in Scotland’s interest will use the powers it already holds.

Write to your MSP → Read the evidence